How to Do a Security Risk Assessment for Your Site in Saudi Arabia

A security risk assessment for a site in Saudi Arabia follows seven steps: list the assets, identify threats, walk the site to find vulnerabilities, score each risk on a 5×5 likelihood and impact matrix, choose controls, measure residual risk, then set an action plan with owners, dates and regular reviews, in line with Ministry of Interior and HCIS rules.

Key Takeaways

  • A security risk assessment is a written process that defines what a site protects, the likely sources of harm, their likelihood and impact, and the controls needed.
  • On a 5×5 risk matrix the risk score equals likelihood multiplied by impact, giving a range from 1 to 25, and the highest scores are treated first.
  • Residual risk is the score that remains after new controls are applied, and the site owner decides whether it is acceptable or needs another control.
  • Minister of Interior Decision 5264 of 1446 AH lists Saudi facility types that must keep security guards around the clock or during working hours.
  • A security risk assessment should be reviewed every three to six months and after any incident or expansion.

What is a security risk assessment and when do you need one?

A security risk assessment is a structured study of one specific site that links three elements: the threat, meaning a possible source of harm such as theft, intrusion or vandalism, the vulnerability, meaning the weakness that lets the threat succeed, and the impact, meaning the loss if it actually happens. A real risk exists only when all three meet.

You need one when a new site opens, before you sign with a security company, and after any incident or expansion. This guide explains how to prepare it in house.

How do you list assets and identify threats at your site?

Start with what you protect, then ask for each asset who might target it, when and how.

Step 1: The asset list

  • People: staff, visitors and contractors, always first.
  • Property: stock, equipment, vehicles and cash at points of sale.
  • Sensitive areas: electrical and server rooms, fuel tanks and hazardous material stores.
  • Continuity: what would stop operations if lost.

Step 2: Threat identification

Threats vary by activity. Warehouses in industrial cities face night time cargo theft, construction sites face cable and equipment theft, and shopping centres face shoplifting and seasonal crowding. Add the insider threat from a staff member or contractor with too much access, and fire, which needs early detection.

How do you find vulnerabilities during the site walk?

The site walk is the most valuable input because it shows what drawings do not. Walk it by day and after dark, like someone trying to get in unseen.

Site walk checklist

  • Perimeter fence: are there gaps, low sections or stretches next to vacant land?
  • Gates: how many are really used, who holds the keys, and is a side gate left open without supervision?
  • Lighting: where are the dark spots and corners that no camera covers and no guard can see?
  • Entry: is every visitor logged, and are cards taken back from leavers?
  • Cameras: do they all work, and does anyone actually watch them during the shift?
  • Incident history: what happened in the last year, at what hour and at which point?

How does a 5×5 risk matrix work?

A 5×5 risk matrix is a table that rates each risk on two axes: likelihood from 1 to 5 and impact from 1 to 5. Multiplying them gives a risk score from 1 to 25, so priorities are written down, not guessed.

The likelihood scale

  • 1 Rare: never seen here or at similar sites.
  • 2 Unlikely: rare at similar sites.
  • 3 Possible: could happen within the year.
  • 4 Likely: happens several times a year.
  • 5 Almost certain: happens monthly or more.

The impact scale

  • 1 Insignificant: a small loss, work continues.
  • 2 Minor: a limited loss or hours of disruption.
  • 3 Moderate: a day of disruption or a minor injury.
  • 4 Major: days of downtime or a regulatory breach.
  • 5 Severe: serious injury or a long shutdown.

Reading the score

  • 1 to 4 Low: monitor through normal procedures.
  • 5 to 9 Medium: treat within months.
  • 10 to 16 High: a control, an owner and a near date.
  • 17 to 25 Critical: treat immediately before anything else.

Example: a warehouse back gate stays open at night. Theft through it is likely, 4, with major impact, 4, so the score is 16, a high risk.

How do you choose controls and measure residual risk?

A control is any measure that lowers the likelihood or the impact of a risk, and several layers work better than one.

  • Deter: a visible guard at the gate, signs and good lighting.
  • Detect: patrols at varied times and camera monitoring from the on site control room.
  • Delay: locks, a sound fence, written access rules and visitor permits.
  • Respond: clear escalation instructions for the guard, emergency numbers and a duty manager.

After choosing a control, score the same risk again. In the back gate example, locking it at night with an hourly patrol may cut the likelihood to 2, giving a score of 8. That is the residual risk, which the owner accepts or treats with another control.

How do you write the risk assessment template and action plan?

A security risk assessment template is a spreadsheet with one risk per row and these columns:

  • Risk number and the asset at risk.
  • The threat and the vulnerability that allows it.
  • Current controls.
  • Likelihood, impact and score before treatment.
  • The new control, its owner and the due date.
  • The residual score after treatment and the approval signature.

Sort the rows from the highest score to the lowest and they become the action plan on which the full site security plan is built.

When do you review the assessment?

  • Every three to six months at busy sites.
  • Immediately after any incident or attempted entry.
  • When a building or gate is added or operating hours change.
  • Before peak seasons such as Ramadan, Eid and large events.

Which Saudi requirements should a risk assessment consider?

Start with a legal question: is the site required to have guards at all? Minister of Interior Decision 5264 dated 6/11/1446 AH amended Article 2 of the executive regulations of the Private Civil Security Guard Law, published in the Umm Al-Qura gazette in May 2025.

  • Around the clock guarding: hotels, banks, hospitals, gold shops, markets with 30 or more shops or over 3,000 square metres, and closed residential compounds with more than 10 villas or 50 units.
  • Guarding during working hours: private schools, wedding halls, private clinics and restaurants over 1,000 square metres.
  • Factories and warehouses: the regional police director can require guarding, with a study from a licensed security consultancy within two months.

On industrial and petroleum sites in Jubail, Yanbu and Ras Tanura, HCIS reviews projects and emergency and evacuation plans against its security directives and its safety and fire protection directives. For fire, Civil Defense is called on 911 in Riyadh, Makkah, Madinah and the Eastern Province, and on 998 in other regions. Camera use falls under the Security Surveillance Cameras Law, Royal Decree M/34 of 1444 AH.

Should you do the assessment yourself or use a security company?

You can prepare a first assessment in house, but an outside team sees what your staff have grown used to.

In house assessment

  • Site knowledge: high, since the team knows daily operations.
  • Objectivity: limited, since familiar gaps are often missed.
  • Output: a risk table that still needs a guarding plan.

Site survey with a security company

  • Site knowledge: built during the visit.
  • Objectivity: higher, with experience running similar sites.
  • Output: guard posts, patrols, access rules and shifts.

Qimah Security Guards holds an HCIS Category One guarding licence and offers an on site security survey in Riyadh, Jeddah, Dammam, Jubail and other Saudi cities that turns your findings into a written guarding plan.

Security Risk Assessment FAQs

What are the steps of a security risk assessment?

A security risk assessment has seven steps: list the assets, identify threats, walk the site by day and night to find vulnerabilities, score each risk for likelihood and impact on a 5×5 matrix, choose controls, measure the residual risk, then write an action plan with an owner and a date for each item.

What is the difference between a threat, a vulnerability and a risk?

A threat is the possible source of harm, such as a thief or an intruder. A vulnerability is the weakness that lets it succeed, such as an open gate or a dark corner. A risk is what results when both meet with a real impact. So closing the vulnerability lowers the risk even if the threat remains.

How do I calculate the risk score on a risk matrix?

The risk score is likelihood multiplied by impact, each rated from 1 to 5 on a 5×5 matrix, so the result falls between 1 and 25. Scores of 1 to 4 are low, 5 to 9 medium, 10 to 16 high, and 17 to 25 critical and treated at once.

How often should a security risk assessment be updated?

Most sites update their security risk assessment every three to six months. It is also reviewed at once after any incident, when a building or gate is added, when operating hours change, and before peak seasons such as Ramadan and Eid in Saudi cities.

Is my business required to have security guards in Saudi Arabia?

It depends on the type of site. Minister of Interior Decision 5264 of 1446 AH requires hotels, banks, hospitals, large markets and closed residential compounds to keep guards around the clock, and private schools, wedding halls, clinics and large restaurants to keep guards during working hours. Regional police can also require factories and warehouses to have guards where needed.

Related Reading

Turn Your Assessment into a Ready Guarding Plan